Momentum AMP · Enterprise Implementation

Customer forms & sign-offs

One sequence, one owner at every step: Evaluate before contract; the internal AE Opportunity Record at contract signature; Project Set-up after G1; the Discovery Workbook during discovery; then Scope, Data Accuracy, Testing and Go-Live sign-offs. Customer Success reviews begin after implementation.

Current controlled files are available below.

Forms and sign-offs schedule

InstrumentTypeStageSent whenSent byCompleted byUnlocks
Momentum AMP EvaluateCustomer questionnaireStage 0b Solution shaping · pre-contractBefore contractEnterprise AEAgency sponsorProposal and contract
Momentum AMP AE Opportunity RecordInternal recordStage 1 Handoff · internal handoverAt contract signature, before kickoffNobody — internal only, never sent to the agencyAccount ExecutiveProject Set-up is sent
Momentum AMP Project Set-upCustomer questionnaireStage 2 SetupRight after contract signature, once the AE Opportunity Record is acceptedESC Delivery LeadAgency project managerDiscovery Workbook
Momentum AMP Discovery WorkbookCustomer questionnaireStage 4 DiscoveryDiscovery, after Project Set-up (optional pre-contract path available)ESC Delivery LeadAgency teamScope is written
Momentum AMP Scope Sign-offGate sign-offStage 5 Scope Sign-offEnd of discovery, before buildESC Delivery LeadAgency scope signatoryBuild starts; change control applies
Momentum AMP Data Accuracy Sign-offGate sign-offStage 7 Data MigrationAfter the final trial conversionData Migration LeadAgency data owner and controllerFinal conversion is planned
Momentum AMP Testing Sign-offGate sign-offStage 8 TestingWhen agency testing is completeESC Delivery LeadAgency project managerTraining and go / no-go
Momentum AMP Go-Live Sign-offGate sign-offStage 10 Go-LiveAt the go / no-go meeting, before cutoverESC Delivery LeadAgency decision-makerFinal conversion and go-live
Customer Success reviewCustomer Success instrumentStage 12 Handover · Stage 13 GrowAt handover and each review cycleCustomer SuccessAgency executive sponsor and administratorsOngoing account reviews (not an implementation gate)

What happens, in order

EV · Customer questionnaire (Sheet) · Stage 0b Solution shaping · pre-contract

Momentum AMP Evaluate

Sent to the customer

Agency structure, goals, systems and scope, so the proposal is priced right.

Sent when
Before contract
Sent by
Enterprise AE
Completed by
Agency sponsor
Unlocks
Proposal and contract
Current file
v2.5 · 2026-09-30 · 40 numbered questions/statements
Document link coming soon
AE · Internal record (Sheet) · Stage 1 Handoff · internal handover

Momentum AMP AE Opportunity Record

Internal only — never sent

Internal handover. Sales-to-delivery handover: deal context, classification and every commitment. ESC Delivery Lead accepts it at Gate G1, and Project Set-up is then sent.

Sent when
At contract signature, before kickoff
Sent by
Nobody — internal only, never sent to the agency
Completed by
Account Executive
Unlocks
Project Set-up is sent
Current file
v1.1 · 2026-09-30 · 33 numbered questions/statementsIf the Discovery Workbook was sent before contract (optional path), record the exception in sections 4.5 and 4.6.
Document link coming soon
SU · Customer questionnaire (Sheet) · Stage 2 Setup

Momentum AMP Project Set-up

Sent to the customer

Project team, agency record, staff and producer lists, sign-on.

Sent when
Right after contract signature, once the AE Opportunity Record is accepted
Sent by
ESC Delivery Lead
Completed by
Agency project manager
Unlocks
Discovery Workbook
Current file
v1.2 · 2026-09-30 · 18 numbered questions/statements
Document link coming soon
DW · Customer questionnaire (Sheet) · Stage 4 Discovery

Momentum AMP Discovery Workbook

Sent to the customer

How the agency works today: workflows, data, carriers, finance, reporting.

Sent when
Discovery, after Project Set-up (optional pre-contract path available)
Sent by
ESC Delivery Lead
Completed by
Agency team
Unlocks
Scope is written
Current file
v2.5 · 2026-09-30 · 115 numbered questions/statementsOptional pre-contract path: order 1 → 4 → contract → 2 → 3. Use when an Enterprise prospect needs discovery before pricing, the Evaluate is complete, and there is a named decision-maker and date. Send right after the Evaluate; documents and uploads are not required until the contract is signed. Re-confirm the answers at kickoff before the Scope Sign-off, and record the exception in AE Opportunity Record 4.5 and 4.6.
Document link coming soon
Gate sign-off (Word) · Stage 5 Scope Sign-off

Momentum AMP Scope Sign-off

Sent to the customer

The complete implementation baseline, traced to the questionnaires, discovery sessions, Order Form and sales commitments. Unknowns have an owner and date; custom work has an Engineering feasibility decision.

Sent when
End of discovery, before build
Sent by
ESC Delivery Lead
Completed by
Agency scope signatory
Unlocks
Build starts; change control applies
Current file
v1.5 · 2026-09-30
Document link coming soon
DA · Gate sign-off (Word) · Stage 7 Data Migration

Momentum AMP Data Accuracy Sign-off

Sent to the customer

After the final trial conversion: record counts and samples within the scope-agreed tolerance, trust and bank balances exact, and every exception assigned an owner and resolution.

Sent when
After the final trial conversion
Sent by
Data Migration Lead
Completed by
Agency data owner and controller
Unlocks
Final conversion is planned
Current file
v1.0 · 2026-09-30
Document link coming soon
TS · Gate sign-off (Word) · Stage 8 Testing

Momentum AMP Testing Sign-off

Sent to the customer

Every in-scope deliverable is tested or explained in a production-equivalent environment; no Severity 1 or 2 defect remains open, and each Severity 3 or 4 has a workaround, owner and target date.

Sent when
When agency testing is complete
Sent by
ESC Delivery Lead
Completed by
Agency project manager
Unlocks
Training and go / no-go
Current file
v1.0 · 2026-09-30
Document link coming soon
GL · Gate sign-off (Word) · Stage 10 Go-Live

Momentum AMP Go-Live Sign-off

Sent to the customer

Before final conversion: prerequisite sign-offs, readiness evidence, cutover owners and dates, accepted issues, and the decision (Go / Go with named conditions / Not ready).

Sent when
At the go / no-go meeting, before cutover
Sent by
ESC Delivery Lead
Completed by
Agency decision-maker
Unlocks
Final conversion and go-live
Current file
v1.1 · 2026-09-30
Document link coming soon
Customer Success instrument · Stage 12 Handover · Stage 13 Grow

Customer Success review

Sent to the customer

Owned and sent by Customer Success at handover and each review cycle. Not part of the implementation instrument set.

Sent when
At handover and each review cycle
Sent by
Customer Success
Completed by
Agency executive sponsor and administrators
Unlocks
Ongoing account reviews (not an implementation gate)
Current file
Current controlled files are available below.
sorry we are remolding these forms, coming soon

How they are meant to be used

Standard order
Evaluate before contract → AE Opportunity Record at contract signature → Project Set-up right after signature → Discovery Workbook in discovery → Scope, Data Accuracy, Testing and Go-Live sign-offs.
Optional path: Discovery Workbook before contract
Evaluate → Discovery Workbook → contract → AE Opportunity Record → Project Set-up. Use this only when an Enterprise prospect needs discovery before pricing, the Evaluate is complete, and there is a named decision-maker and date. Send the Discovery Workbook right after the Evaluate; documents and uploads are not required until the contract is signed. Re-confirm answers at kickoff before Scope Sign-off and record the exception in AE Opportunity Record sections 4.5 and 4.6.
Ask once
No question repeats across forms. Every form opens with Agency name, Your name, Your email and Your title; agency name is pre-filled from the Evaluate.
File names
Prefix + question number_agency name_short description, e.g. SU2.2_SmithInsuranceGroup_BrandAssets. Prefixes: AE · EV · SU · DW · DA · TS · GL.
The AE Opportunity Record is internal
The internal sales-to-delivery handover, completed by the Account Executive at contract signature, before kickoff. ESC Delivery Lead's acceptance is Gate G1 and unlocks Project Set-up. Never sent to the agency.
Customer Success review sits outside implementation
Owned and sent by Customer Success at handover and each review cycle. It is not part of the implementation instrument set.

Each form also appears against its stage in the process and in Documents. Adding the link in one place makes it show up everywhere.