Program timeline
Enterprise Implementation Lifecycle & Milestone Roadmap
Every workstream on one illustrative 20-week grid — Initiation through Transition — with milestone diamonds for approvals, deliverables and decision points, and a cutover marker separating the pre-cutover build from post-cutover hypercare. Filter by workstream or lifecycle stage, and export the roadmap as an image or PDF for internal and customer stakeholders.
Illustrative 20-week shape within a typical 2–6 month journey · Order Form Part H carries the projected Target Go-Live Date
Enterprise Implementation Lifecycle & Milestone Roadmap
11 of 11 workstreams · 13 milestones · W1–W20
Initiation
Handoff, internal kickoff, customer kickoff
Stages 1–3 · Delivery Lead
Discovery & scope
Current-state discovery, scope document drafted
Stages 4–5 · Delivery Lead and Engineering Authority (joint solution architecture)
Configuration build
Agency structure, workflows, policy and commission configuration
Stage 6 · Data Migration Lead / MAC Specialist
Data migration
Extract, map, load, reconcile
Stage 7 · Data Migration Lead
Integrations
Elected Part F integrations configured and validated
Stage 6–8 · Engineering Authority
Testing & UAT
Test scripts, defect triage, customer acceptance
Stage 8 · Delivery Lead
Training
Begins after Testing Sign-off — design and delivery per elected Part G category
Stage 7–9 · Training Lead
Cutover
Go / no-go, freeze, final load, go-live
Stage 10 · Delivery Lead
Hypercare
Daily standups, issue burn-down, stabilization
Stage 11 · Delivery Lead + Support team
Transition to CSM
Risk register at zero, account handover, first QBR set
Stages 12–13 · Customer Success Manager
Custom development (if required)
ConditionalAlternative route. Only runs when discovery surfaces a requirement configuration cannot meet: scoping request, engineering scope, signed Custom Development SOW and Change Order, build, internal QA, then customer acceptance inside UAT. Accounts with no custom work simply do not have this row.
Stages 4–8 · Engineering Authority (build) · Delivery Lead (template & status)
- W1Contract sign-offApproval · Initiation
- W5Custom development request raisedDeliverable · Custom development (if required)
- W6Scope document sign-offApproval · Discovery & scope
- W8Configuration baselineDeliverable · Configuration build
- W8Custom Development SOW & Change Order approvedApproval · Custom development (if required)
- W12Data correctness sign-offApproval · Data migration
- W14Curriculum deliveredDeliverable · Training
- W14Custom development acceptedApproval · Custom development (if required)
- W15Testing passedApproval · Testing & UAT
- W15Go / no-go decisionDecision point · Cutover
- W16Go-live / cutoverDeliverable · Cutover
- W19Hypercare exitDeliverable · Hypercare
- W20Handover acceptedApproval · Transition to CSM
Illustrative standard program shape. Week positions are planning guidance only — the projected Target Go-Live Date lives in Order Form Part H and becomes a commitment at the Stage 5 scope sign-off. The complete journey from signature through hypercare and formal handover typically takes two to six months.
The dashed Custom development row is an alternative route, not standard work. Most enterprise accounts never trigger it. It only opens when discovery surfaces a requirement configuration cannot meet, and it only proceeds once a Custom Development SOW and Change Order are signed. For an account with no custom work, read the roadmap without that row.